Thermoelectric Cooler for sale | Kingka

A thermoelectric cooler is chosen when the application has to move between set points rather than sit at one: heating and cooling from the same device, with the direction set by current. This module is built for that duty cycle, where the elements see repeated thermal stress and the joints, not the ceramics, decide the life.

The construction is deliberately conservative - bismuth telluride elements between thermally conductive aluminium oxide ceramics, assembled to reduce the stress the elements see in operation. There is no compressor, no refrigerant and no moving part, so the module runs without sound or vibration.
Availability:
facebook sharing button
twitter sharing button
line sharing button
wechat sharing button
linkedin sharing button
pinterest sharing button
whatsapp sharing button
sharethis sharing button

tec

Construction and Materials

Bismuth telluride semiconductor pellets are arranged between two aluminium oxide ceramic plates, joined with solder, and sealed with leads brought out for the DC supply. The pellet pattern and the joint thickness are set so that differential expansion during cycling loads the elements as little as possible.

Key Characteristics

Cycling duty

Built for repeated set-point changes.

Bismuth telluride elements

Semiconductor pellets, not a refrigerant.

Alumina ceramics

Thermally conductive, electrically isolating.

Solid state

No sound, no vibration, no service parts.

Precise control

Direction and magnitude set by current.

Technical Specifications

Base Material Bismuth telluride elements between alumina ceramic plates
Elements Bismuth telluride semiconductor
Ceramic Thermally conductive aluminium oxide
Operation Solid state, no sound or vibration
Use Cycling between several set points
Base CNC Tolerance Milling / drilling / tapping down to +/-0.005 mm
Dimensional Inspection Hexagon CMM +/-0.001 mm; 2.5D optical projector
Quality System ISO 9001:2015; IATF 16949:2016
Capacity 60,000+ thermal parts per year
Lead Time Samples typically 7-15 days; production scheduled to volume

Note: values above are KingKa build options and verified capability; final geometry, holes and finish are confirmed against your drawing.

Process and Quality Control

A TE module is rated by dT, not by wattage alone: the same module that moves 50 W at dT = 10 C moves far less at dT = 40 C, so the count follows the dT the application actually asks for.

Process flow

  • Duty review. Hot-side temperature, dT and cycle profile define the module count.

  • Pellet assembly. Bismuth telluride pellets placed and soldered between ceramic plates.

  • Sealing and leads. Module sealed and leads brought out for the DC supply.

  • Cycling check. Sample modules cycled against the customer profile.

  • Final test. dT, resistance and insulation verified before packing.

What we verify on every batch

  • dT at rated current - measured on a hot-side fixture.

  • AC resistance - checked per module.

  • Insulation - ceramic-to-element isolation tested.

  • Cycle endurance - verified against the agreed profile.

  • Visual and dimensional - flatness of both ceramic faces.

Application Scenarios

Cycling coolers are used where temperature has to move, not just hold:

  • Healthcare analysers

  • Laser diode packages

  • Sample storage chambers

  • Analytical instruments

  • Precision optics

Customization and OEM Service

Send the hot-side temperature, the required dT, the cycle profile and the footprint. KingKa sizes the module count to the dT, then sets the ceramic and joint for the cycle count you need.

Procurement Advantages

KingKa is a direct manufacturer with 16+ years in thermal production, 50+ CNC centers, in-house skiving, FSW and vacuum brazing, certified to ISO 9001:2015 and IATF 16949:2016.

Give the cycle profile with the dT - cycling life is set by the profile, and the module has to be selected for that profile rather than for a catalogue wattage.

  • One supplier for the whole assembly. Base, fins, pipes and hardware under one quality system.

  • CFD before tooling. Design review catches a bad layout before metal is cut.

  • Prototype to volume. Samples in 7-15 days, production scheduled to forecast.


Previous: 
Next: 
Get a Quote Now

PRODUCTS

QUICK LINKS

CONTACT US

   Tel: +86 13712444018 
   E-mail: sales2@kingkatech.com 
    Add: Da Long Add: New Village,Xie Gang Town, Dongguan City, Guangdong Province, China 523598
Leave a Message
Get a Quote Now
Kingka Tech Industrial Limited    All rights reserved     Technical Support: Molan Network